The Next Steps We're Taking

ATLNext has a lot of moving pieces. We want to keep you informed of what we're working on now, what's coming up and how it all impacts you. Check in regularly for updates on our progress!

North Terminal

Driving Experience

Parking Experience

Driving Experience

Now through Summer 2019

South Terminal Roadways

Lane Closure(s):

  • There are partial lane closures as construction of the North canopy comes to a close.  Drivers are encouraged to use the Express Drop-off area at the North Lower Level.

Rideshare North Pickup Location 
Relocation:

  • The North Pickup location is operating out of the North Daily lot.  Please use the orange navigation signs near North baggage claim areas.

Parking Experience

Parking is not impacted at this time.

South Terminal

Driving Experience

Parking Experience

Driving Experience

Now through Fall 2019

South Terminal Roadways

Lane Closure(s):

  • All lanes on the Airport’s South roadway will reopen on October 2019, with only nightly partial roadway closures causing minimal impacts as South canopy finishes are completed.

Rideshare North Pickup Location 
Relocation:

  • The South Rideshare and International Terminal pickup areas will remain unchanged.

Parking Experience

Now through Fall 2019

South Parking Facilities 

Temporary Relocation of Exit(s):

  • Exits to various parking facilities may be impacted by the ongoing construction of the canopy on the South side.