Hartsfield-Jackson Prepares for Busy Holiday Travel Period

More than 3.7 million passengers expected to travel through ATL As the world’s busiest and most efficient airport prepares for a robust holiday travel period, Airport construction officials will halt most public-facing work to ease traffic concerns. Hartsfield-Jackson Atlanta International Airport (ATL) expects to serve more than 3.7 million passengers during the holiday period that … Continue →

South Canopy Construction Efficiencies

South Roadway traffic to be impacted; alternate options suggested Three steel columns supporting the South roadway canopy were successfully placed overnight on Oct. 16, and lessons learned from the North canopy installation have already been implemented one night into South canopy construction. Monday night into Tuesday morning, the placement of the columns on the South … Continue →

North Canopy nearly complete, South Canopy construction to impact traffic

Saturday, Oct. 6 marks a major milestone in the construction of ATL’s North Canopy. All lanes on the Airport’s North roadway will reopen and commercial vehicle traffic – moved to the South roadway during the construction process – will be relocated to the North curb. The focus of canopy construction will now turn to the … Continue →

Canopy Construction Ongoing, South Roadway Soon Impacted

As construction on the North canopy completes, the South roadway will become the focus of canopy building efforts. Roadways closed during North canopy work will soon reopen, while portions of the roadway leading to the South Terminal will temporarily close. The vast majority of construction will take place overnight, but late-night passengers – either departing … Continue →

ATLNext Moves Ahead on Canopies

All structural steel for the North canopy has been erected. Nineteen steel supertrusses on the North canopy were constructed from October 2017 to May 2018. Check it out!

ATLNext moves ahead on canopies, parking, terminal

Enhancements to the world’s busiest and most efficient airport are happening 24/7 as Hartsfield-Jackson’s multibillion-dollar capital improvement program continues. Read below for activity updates on several ATLNext projects. Canopy – North All structural steel for the North canopy has been erected. The canopy covering in the first bay is planned to start right after Memorial … Continue →

Canopy Construction to Impact North Hourly Parking Exit

Temporary change to last through September 2018 Hartsfield-Jackson officials will temporarily move the North hourly parking lot exit beginning 12:01 a.m. Monday, March 26. During this time, North hourly lot customers will instead utilize the same exit plaza as daily and economy parkers. Additional parking staff will accommodate the adjustment. The North hourly lot entrance … Continue →

ATLNext Industry Day Presentations

2019 Industry Day Presentations Track 1.1-Procurement Track 1.2-Compliance Track 1.3-Ethics Track 2.1-Safety Track 2.2-Security Track 2.3-Environmental Track 2.4-CPTC Track 2.5-Parking Deck Track 3-Overview