The Next Steps We're Taking

ATLNext has a lot of moving pieces. We want to keep you informed of what we're working on now, what's coming up and how it all impacts you. Check in regularly for updates on our progress!

North Terminal

Driving Experience

Parking Experience

Driving Experience

Through June 2018

North Terminal Roadways
Lane Closure(s):

  • Daytime closure of the upper outer roadway
  • Nightly closure of either upper outer roadway or partial upper and lower roadways

Commercial Vehicle Drop-Off Relocation:

  • Temporary relocation of North Terminal hotel and parking shuttle drop-offs to the South Terminal. Use door S4 to walk through the Atrium for North airlines’ check in.

Parking Experience

Parking is not impacted at this time.

South Terminal

Driving Experience

Parking Experience

Driving Experience

June 18 to November 30

South Terminal Roadways
Lane Closure:

  • Daytime and nightly closure of the outermost lane of the upper roadway
  • Daytime and nightly partial lane closure of lower roadway

Parking Experience

Parking is not impacted at this time.